Project Timeline

March 2019

Cranberry Point Energy Storage LLC presented to the Town of Carver’s Planning Board and Conservation Commission and received approval of the project’s Site Plan and Special Permit and Order of Conditions, respectively

December 2020

Plus Power updates the Carver Conservation Commission of minor modifications; no update or change to the Order of Conditions is necessary or required.

February 2021

Cranberry Point clears the ISONE Forward Capacity Auction (FCA) and secures a 7-year Capacity Supply Obligation to provide capacity for ISONE

May-April 2021

Plus Power updates the Town of Carver’s Planning Board about the project status and requests a two-year extension for the Site Plan and Special Permit to align with the anticipated construction start in 2023; the extension was granted.

May-June 2021

Plus Power submits a Minor Modification Application to the Town of Carver’s Planning Board for the updated and improved site design. The minor modification application was approved as a static facility located over 800 feet off of Main Street.

August 2021

Petition for Approval to Construct the Cranberry Point Energy Storage Project submitted to the Massachusetts Energy Facilities Siting Board (EFSB)

August 27, 2021

Link to EFSB Petition filed August 27, 2021 as Docket EFSB21-02

To access the EFSB Petition after clicking the button above, type in “EFSB21-02” to the “Enter docket number…” field.

November 8, 2021 at 7:00pm

EFSB Public Comment Hearing for Docket EFSB21-02

May 2023

Carver grants Special Permit Extension

MA EFSB transitioned Cranberry Point’s 40A permit application to the MA DPU

June 2023

MA DPU approved the project’s 40a permit application.

December 2023

Construction start

Early 2025

Commercial Operation Date

 

Construction Information

Details regarding the construction of the
Cranberry Point Energy Storage project:

  • When is the Project scheduled to start construction? December 2023

  • What is the Project’s anticipated construction duration? 12-15 months

  • What are the hours of construction? Monday through Friday from 7:00 am to 4:30 pm, with an exception if there are emergency circumstances on a given day that necessitate work beyond these hours.

  • Notice regarding construction linked here

    Please check back periodically for updated notices during the construction phase of the Project.

Local Outreach

After years of public presentations, public notifications for public hearings, and receiving comments at the local and state level since 2018, Cranberry Point Energy Storage received the final permits needed in 2023.

Since 2018, several presentations have been made to the Carver Conservation Commission and Planning Board. In March 2019, the Planning Board voted 4-1 in support of Cranberry Point and the current 2021 Planning Board voted unanimously to extend the validity of the Site Plan and Special Permit to March 31, 2023. Additionally, the Planning Board voted to approve the Minor Modification Application submitted by Plus Power in June 2021. Plus Power has also presented to the Carver Conservation Commission, hosted the 2021 Planning Board and Town Administrator for a site visit, shared its plans with area elected officials, and hosted a July 13, 2021 meeting for abutting neighbors.

In May 2023, the Carver Planning Board voted 3-2 to extend the validity of the Site Plan and Special Permit to May 2024. Also in May 2023, the Massachusetts Energy Facilities Siting Board (EFSB) transitioned for approval the permit application for Cranberry Point Energy Storage to the Massachusetts Department of Public Utilities (DPU). In June 2023, the Massachusetts DPU issued an order approving the project. A notice of the commencement of construction was sent to abutters, and the project website was updated to identify the start of construction.
Operation of the facility is anticipated to commence in early to mid-2025, allowing Cranberry Point Energy Storage to initiate support of the local electric grid.

Community Benefits

Cranberry Point will be a good neighbor and a valuable asset to the surrounding community for decades to come. The project will provide necessary capacity to the Commonwealth with no air-polluting emissions. As a static facility located over 800 feet off of Main Street, with insignificant traffic and minimal municipal services, Cranberry Point will have little impact on adjacent properties. Significant project benefits to the community include:

  • High-paying construction jobs

  • Enhanced electrical grid resiliency from a new, state-of-the-art power resource

  • Expanded property tax base for the local district